Boundary Dam Power Station
coal-fired station located near Estevan
six units with a combined generating capacity of 813 net MW
two 62 net MW units commissioned in 1959
two 139 net MW units were added in 1970
one 139 net MW unit was added in 1973
one 273 net MW unit was added in 1978
a long term project to install electrostatic precipitators on all units
— to reduce air particulate emissions — was completed in July
2003