Construction and Project Schedule
Construction is scheduled to begin in August 2009 and to be completed by the end of December 2009.
Project Schedule
January to June 2007 – Alternative corridor selection
June 5-14, 2007 – Meetings with local town, rural municipality and City of Moose Jaw officials
June 18-21, 2007 – Public open house meetings in Coronach, Willow Bunch, Bengough and Moose Jaw
July to Fall 2007 – Secondary environmental screening
February 2008 – Preferred corridor selection and a second series of stakeholder meetings
Fall 2007 to Summer 2008 – Environmental field studies
December 2008 – SaskPower submits an Environmental Impact Statement (EIS) for this project to Saskatchewan Environment
October 2008 to February 2009 – Engineering design
March to July 2009 – Fabricate structures and obtain easements
August to December 2009 – Construction
Construction and Project Schedule