Introduction
SaskPower’s Electric Service Requirements have been prepared to provide requirements for the connection of electrical service to SaskPower’s facilities. The basic intent of these requirements is to ensure conformity to the Code, provide for protection of personnel and equipment, and recognize operational needs; while providing as many options as reasonable for the connection of electrical service to SaskPower's facilities.
SaskPower Electrical Inspections Division, by the authority of the Electrical Inspection Act for Saskatchewan and the Canadian Electrical Code, Part I, and Saskatchewan Amendments, has complete authority beyond the point of delivery.
In addition to Code requirements, the Electric Service Requirements cover SaskPower's requirements. If not followed, the service request may be refused as SaskPower has an obligation to ensure public safety and maintain service standardization.
Requests for deviations to the Electric Service Requirements must be made in writing to the applicable SaskPower customer service office. In order for SaskPower to properly consider the request, it must be accompanied by drawings and must be received well in advance of construction. For contacts and telephone numbers, please see the customer services area map, as found near the end of Section 1. If approval for a deviation is granted by SaskPower, it is only valid for the particular service in question, and is not a general approval for any future services.
If you would like to be notified, by email, of any changes to SaskPower's Electric Service Requirements please provide the required contact information.
Suggestions for changes to the Electric Service Requirements must be made in writing, using the "Request For Change Form", and mailed or faxed directly to:
|