Completed Projects

Print this page Make font smaller Reset font size Make font larger

Sustainable Growth

Transmission and Distribution

TransCanada Pipelines Keystone Liebenthal Transmission Line – 230kV transmission line
InProvided service to a new TransCanada Pipelines pumping station five kilometres east of Liebenthal.
Completed October 2010

BHP Billiton Jansen – 138kV transmission line
Installed a temporary transmission line to the BHP Billiton potash mine for 3-5 years.
Completed September 2010

TransCanada Pipelines Keystone Stewart Valley Transmission Line – 138kV transmission line
Provided service to a new TransCanada Pipelines pumping station eight kilometres northeast of Pennant.
Completed September 2010

Steelman – 138kV transmission line
Connected the Boundary Dam Switching Station to the Steelman substation.
Completed July 2010

Poplar River to Pasqua – 230kV transmission line
Connected the Poplar River Power Station to the Pasqua Switching Station.
Completed October 2009

James Richardson International/Louis Dreyfus – 138 kV transmission line
Provided electricity to two new canola-crushing facilities near Yorkton.
Completed May 2009

IslandFalls-Pelican Narrows – 25/110 kV transmission line
Improved service in the Pelican Narrows and Deschambault Lake area.
Completed August 2008

Enbridge Kerrobert – 138 kV transmission interconnection
Linked the NRGreen heat recovery Environmentally Preferred Power project to the provincial power system.
Completed November 2007

ML3 Rebuild Stage 4 (Meadow Lake) – Beauval 72/138 kV transmission line
Improved reliability and quality along the Meadow Lake and north corridor.
Completed June 2006

Rushlake Creek – 230 kV transmission interconnection
Connected the 150 MW Centennial Wind Power Facility to the provincial power system.
Completed September 2005

Parkridge Tap – 138 kV transmission line and substation
Reinforced fast-growing east Regina.
Completed May 2005

Kindersley-Marengo – 138 kV transmission line
Addressed the growing demand from the oil and gas sector in west-central Saskatchewan.
Completed April 2004

Generation

Ermine Switching Station Simple Gas Turbines – 94 MW
Energized two new General Electric Energy turbines.
Completed July 2009