self generation power equipment

Non-exporting self-generation allows you to offset a portion of the power you use with a generation system that’s located at your home or business. With this generation option, unused power isn’t sent back to the grid. All the power you generate must be used in real time or saved for later with a storage solution. You can use renewable sources, like solar or wind, or non-renewable sources, like natural gas.

Non-Export Self Generation applies to projects under 1 megawatt (MW) that connect to SaskPower’s distribution system. If your project is 1 MW or larger, or your site connects to the transmission system, you must apply through the Transmission Interconnection Process.

Planning a non-export self-generation project? Review the process, costs, timelines, and requirements below before purchasing equipment or signing contracts.

Process Overview

Follow the steps below to apply for and install a non-export self-generation system. Understanding the process before you apply can help you plan your project, avoid delays and understand any requirements or costs that may apply.

  1. Decide if Non‑Export Self‑Generation is right for your needs.
  2. Apply to SaskPower and contact the Technical Safety Authority of Saskatchewan (TSASK) to confirm inspection requirements.
  3. SaskPower reviews your application and completes an interconnection study.
  4. Review the study results, including any required upgrades and costs.
  5. Decide whether to proceed and sign the Generator Interconnection Agreement.
  6. Install your system and complete all required inspections.
  7. Energize your system once all approvals are complete.

Things to Consider

Before you invest in a generation system, it's important to understand the timelines, costs, approvals, and technical requirements involved. Reviewing these considerations early can help you make informed decisions and determine whether a project is right for your needs.

Developing a generation project takes time and effort. Many factors can affect your timeline. Here are some key points to consider:

  • Interconnection study: SaskPower must review how your project connects to the grid and how it may affect other customers. This interconnection study can take up to 6 months and may require design updates and back‑and‑forth with your installer or engineer.
  • SaskPower work: If upgrades to SaskPower’s system are required, this work can take from 1 month to more than 2 years, depending on what’s needed (for example, a new meter or substation upgrades). You’ll receive a schedule after the interconnection study is complete.
  • Project changes: If you significantly change your project after the study, you’ll need to submit a new application. The cost and timeline will also change.
  • Approvals required: Your project must be approved by both SaskPower and TSASK.

Before buying equipment or signing contracts, understand the costs connected to your project.

  • Interconnection study fee:
    • Under 5 kilowatts (kW) = $0
    • 5kW to 100 kW = $300 + taxes
    • Over 100 kW and under 1 MW = $1,000 + taxes
  • Interconnection costs:
    • SaskPower may need to make changes to the power system to safely connect your generation.
    • You’re responsible for paying for any required upgrades.
    • These costs are identified through the interconnection study.
    • Costs vary based on generation type, system size, location, and equipment used.
    • Some projects may have high cost (ranging from hundreds to millions of dollars), which could affect whether the project makes sense for you.

  • SaskPower and TSASK are separate organizations. Both must approve your project before it can be energized. TSASK reviews your system for electrical safety. SaskPower reviews how your project connects to the power grid.
  • Even though these projects are called non‑export, in certain circumstances some electricity may still flow to the grid. An interconnection study is required to confirm the system can connect safely.
  • Interconnection costs and requirements may influence the overall feasibility of your project. Avoid major contracts or financial commitments until SaskPower provides study results showing required upgrades, costs, and timelines.
  • In some cases, SaskPower may not approve your project moving forward because of safety and reliability issues in your location. It’s important for you to wait for the interconnection study to be completed before advancing with purchasing and installing the equipment.

  • Your system can reduce how much electricity you buy from SaskPower.
  • It will not eliminate your power bill. You will still pay the Basic Monthly Charge.
  • You will not receive bill credits because excess power is not sent to the grid.
  • When your system doesn’t produce enough power, you’ll use electricity from SaskPower's grid and be billed as usual.

Before adding generation, consider energy efficiency options. These may cost less and reduce power bills. Improving efficiency first, can also reduce the size and cost of a generation project. 
Check out our programs for more information at Power Savings and Programs.

You can also learn more about the Non-Export Self Generation by visiting our FAQs page.

Ready to Apply? 

Is your project under 1 MW and connected to the distribution system?

Use the Net Metering application to apply. There’s no separate application form for non-export self-generation projects.

While filling in the application, be sure to:

  • Indicate 'non-export self-generation' in the comments section.
  • Attach:
    • Site plan
    • Single line diagram
    • Equipment specifications sheets

Projects greater than 100kW AC must also complete and attach a copy of the Interconnection Service Request - Generation form (Appendix B of the Generation Interconnection Requirements at Voltage 34.5 kV and Below document)

APPLY NOW

Is your project 1 MW or larger, or connected to the transmission system?

Apply through the Transmission Interconnection Process.